Councilmembers Herbold and Pedersen Respond to West Seattle Bridge Remaining Closed through 2021

Home » Councilmembers Herbold and Pedersen Respond to West Seattle Bridge Remaining Closed through 2021

SEATTLE – Councilmember Lisa Herbold (District 1 – West Seattle/South Park) and Councilmember Alex Pedersen (District 4 – Northeast Seattle and Chair of Transportation & Utilities Committee) issued the following statement regarding the ongoing and extended closure of the West Seattle Bridge:

“Today we learned from the Seattle Department of Transportation (SDOT) that, while the rate of cracking of concrete under the West Seattle Bridge has slowed, new cracking continues even with no vehicles.  Unfortunately, SDOT now estimates the bridge cannot be made safe for traffic for at least the next 21 months (through the end of 2021). Safety will continue to be the top priority during this infrastructure emergency. SDOT is developing plans to shore up the bridge in advance of the likely extensive repairs. SDOT believes, however, that repairs would extend the life of the bridge for only 10 years.

“The impact of this long-term closure on West Seattle cannot be understated. We will need additional work to manage traffic and mobility for residents. Ensuring access to emergency services and transit will be critical as well. What we are doing now to provide alternate routes will not be sufficient once traffic resumes normal levels.

“We look forward to working with our State and federal governments to identify the funding for both the repairs and the eventual replacement of the bridge, including an expected stimulus package for infrastructure from Congress. This situation also reinforces the importance of renewing the Seattle Transportation Benefit District to provide additional bus service.

“It’s good that SDOT is creating a technical advisory panel to leverage engineering expertise.  The City Council’s Transportation & Utilities Committee will require timely updates from both SDOT and the technical advisory panel.  We will also pursue Legislative Department participation on the technical advisory panel to increase oversight of the complex solutions.”

###

Presentation: For SDOT’s April 15, 2020 presentation to update the media on the condition of — and plans for — the West Seattle Bridge, CLICK HERE.

SDOT: For more information on the West Seattle Bridge, please see SDOT’s website by CLICKING HERE.

West Seattle Blog: For updates from the detailed West Seattle blog, CLICK HERE.

Councilmember Pedersen: For his original March 23, 2020 blog post on closure of West Seattle Bridge, CLICK HERE.